Auto-scheduling lets the Gantt automatically move tasks forward whenever an upstream task changes. When enabled, any task linked by a Finish-to-Start dependency is rescheduled so it starts no earlier than its predecessor ends. This removes the need to manually adjust dates throughout a dependency chain.

The schedule Prop

Pass a schedule object to the <Gantt> component to configure scheduling behaviour.

The summary Prop

The summary prop controls automated behaviour for summary (parent) tasks.

Forward Scheduling Mode

In forward scheduling mode (type: "forward"), the engine starts from the project start date and propagates task dates forward along the dependency chain:
  1. Tasks with no predecessors are placed at the projectStart date.
  2. Each Finish-to-Start (e2s) link causes the target task to start on or after the source task’s end date.
  3. If auto: true, this recalculation runs on every task edit, drag, or resize.
Links with a lag value are respected — the target task starts lag working days after the source ends (when a calendar is configured).

Basic Example

The demo below enables auto-scheduling with a fixed project start date. Moving or resizing any task propagates the change through the dependency chain automatically.

How Finish-to-Start Scheduling Works

When schedule.auto is true, every e2s (end-to-start) link is evaluated after each change:
  • The source task finishes at a calculated date.
  • The target task start is pushed to match or exceed the source end date.
  • The target’s end date shifts by the same offset, preserving duration.
  • The cascade continues down the dependency chain recursively.
Combine schedule with the Calendar prop so that scheduling respects working days and hours. Durations are measured in working time when a calendar is active.

Controlling Project Bounds

Use projectStart and projectEnd props to constrain the scheduling window:
Tasks will not be scheduled before projectStart. The projectEnd date is used by the Critical Path engine to identify late tasks.